updated JUly 22, 2025

Amin nga Update ti Housing & Permitting

Datos manipud iti

323

Ti Maproseso

Dagup a Building Permits nga Agproseso

182

Residensial nga

141

Saan a pagnanaedan


Application for permit has been submitted and is being processed

453

Nairuar

Dagup a Naited a Building Permits

421

Residensial nga

32

Saan a pagnanaedan


Permit has been issued, but not yet completed.

42

Nalpasen

Nakompleto ti Dagup a Building Permits

42

Residensial nga

0

Saan a pagnanaedan


Permit has been completed, with home having passed final inspection and ready for habitation.

275

In Construction

Dagup dagiti Balay a Maibangbangon

*Non-Residential includes commercial properties, properties with 4 or more dwelling units, and all Puamana permits.

updated JUly 22, 2025

Lahaina Pammalubos nga Updates

Datos nga inted ni

322

Ti Maproseso

Dagiti Pammalubos ti Panagbangon iti Proseso

181

Residensial nga

141

Saan a pagnanaedan


Application for permit has been submitted and is being processed

443

Nairuar

Naited ti Building Permit

411

Residensial nga

32

Saan a pagnanaedan


Permit has been issued, but not yet completed.

38

Nalpasen

Nalpasen dagiti Building Permit

38

Residensial nga

0

Saan a pagnanaedan


Permit has been completed, with home having passed final inspection and ready for habitation.

updated JUly 22, 2025

Dagiti Panagpabaro ti Pammalubos iti Upcountry

Datos nga inted ni

1

Ti Maproseso

Dagiti Pammalubos ti Panagbangon iti Proseso

1

Residensial nga

0

Saan a pagnanaedan


Application for permit has been submitted and is being processed

10

Nairuar

Naited ti Building Permit

10

Residensial nga

0

Saan a pagnanaedan


Permit has been issued, but not yet completed.

4

Nalpasen

Nalpasen dagiti Building Permit

4

Residensial nga

0

Saan a pagnanaedan


Permit has been completed, with home having passed final inspection and ready for habitation.

updated JUly 22, 2025

TDS/PDS Progress Tracker

Debris Transfer Progress

Started

50%

Complete

The above graphic is an estimate of progress made, but may not be a precise representation of the percent transferred.

Amin nga Update ti Panagikkat ti Debris

Datos nga inted ni

Before

Debris Removal Front Street Pilings

After

Debris Removal Front Street Pilings

100% Complete

Linya ti Imburnal ti Kalsada Fleming ti Kealamoka

Petsa ti Panangrugi: 10 HUL 24 (Naipaay)
Napadpadaanan a Pannakaileppas: 15 MAR 25

1500/1500 LF 8” imburnal kangrunaan ti naikabil
1000/1000 LF 12” imburnal kangrunaan ti naikabil
26.5/28 nga lateral ti imburnal ti naikabil
11/11 dagiti manholes ti imburnal

100% Dagiti Lote ti Pagtaengan

Para kadagiti Residential Properties

Petsa ti Panangrugi: 05 ENE 24
Petsa ti Panagleppas:
11 SEP 24

Dagup a Lote: 1390
Lote nga Na-clear: 1390
Lote nga Kompleto: 1390

100% Komersyal nga Lote

Para kadagiti Komersio/Public Properties

Petsa ti Panangrugi: 27 PEB 24
Petsa ti Panagleppas:
26 PEB 25

Dagup a Lote: 148
Lote nga Na-clear: 148
Lote nga Kompleto: 148
Shoring & Bracing Dagiti Naipakasaritaan nga Estruktura: 6 ti 6

Adda Saludsodyo?

Awaten ti Kondado ti Maui dagiti saludsod ken feedbackyo tapno makatulong a mangiwanwan kadagiti panagregget iti panangipaay kadakayo ken iti komunidad iti kaaduan a makagunggona nga impormasion.

Mariknayo a nawaya nga ag-email iti support@mauirecovers.com a direkta.

Mahalo iti panangibinglaymo kadagiti komento ken feedback. Agsubli ti team-mi kadakayo iti mabiit.

Uy, ni! Adda nagbiddut bayat ti panangisubmitir iti porma.

Adda Saludsodyo?

Awaten ti Kondado ti Maui dagiti saludsod ken feedbackyo tapno makatulong a mangiwanwan kadagiti panagregget iti panangipaay kadakayo ken iti komunidad iti kaaduan a makagunggona nga impormasion.

Mariknayo a nawaya nga ag-email iti support@mauirecovers.com a direkta.

Mahalo iti panangibinglaymo kadagiti komento ken feedback. Agsubli ti team-mi kadakayo iti mabiit.

Uy, ni! Adda nagbiddut bayat ti panangisubmitir iti porma.